There are several ways to delete tasks in projects:

  • Using the Tasks screen or Gantt screen in a project
  • Using the Staff Planner or Resource Planner


Deleting Tasks Using the Tasks Screen or Gantt screen

To delete a task in Projectal, follow these steps:


  1. Go to the Projects screen by clicking Projects on the left sidebar.
  2. Find the project you wish to work on and click on it to enter the project.
  3. Click on Tasks or Gantt on the left sidebar to enter the Tasks view or Gantt view of the project.
  4. Select a task and click the Delete Task button on the Tasks screen toolbar or Gantt screen toolbar.
  5. You will be asked to confirm the deletion.


Deleting Tasks Using the Staff Planner or Resource Planner

To delete a task using the Staff Planner or Resource Planner, follow these steps:


  1. Click on Planner on the left sidebar and select the Staff Planner or Resource Planner.
  2. Select a task that you wish to delete and click the Delete button on the Planner screen toolbar or press the DEL key.
  3. You will be asked to confirm the deletion.


Warning: Once the task has been deleted, it cannot be retrieved.  All use of this task in its project will be removed.


Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article